by Marv Carlton, Building Trades Instructor

We have just finished shingling the roof and are now on the inside doing framing in preparation for drywall. At this point, the plumbing, HVAC and electrical are completely roughed in, the basement floor has been poured and the basement stairs have been installed.

Micah D. nailing a 45 degree corner
on an angle wall.
Cody A. with Tyler B. screwing
2" x 4" studs to the concrete
foundation next to the basement stairs.
Erik P. is relocating the doorway at the top of the basement stairs.
Andrew H. takes a measurement for
angle backing in the upper corner
of the master bedroom tray ceiling.

We are currently in the process of building the bay window in the breakfast area, framing five arched openings in various places, and finishing up the tray ceiling in the master bedroom.

In about one week, after we have done a few other minor miscellaneous things, we will be ready for our rough inspection. Once that has passed, we can proceed with insulation and then drywall.

Cody A. & Colin C. are building the
walls for the bay window of
the breakfast area.
Jared C. is nailing the elliptical arch
to the opening of the dining room
doorway (this is one of the five
throughout the house).
Dan M. is nailing the arch in place
in the foyer.
Erik P. is working on the front
door installation.
Andrew H. is installing the lockset
on the front door.